KIRTIPUR, July 29: The first phase of construction at the Tribhuvan University (TU) Cricket Ground in Kirtipur will be completed within a month, according to the contractor. This update was provided to a federal parliamentary monitoring committee that visited the site on Monday to review progress, including parapet and floodlight installation.
Urban Development Ministry Secretary Gopal Prasad Sigdel informed the delegation, led by Committee Chair Thakur Gaire, that 80% of the first phase is done. Of the 12 planned seating blocks, 10 are completed, with seats installed. The remaining 1,700 seats are being imported from India. Once finished, the stadium will seat 10,000 spectators in phase one, and 25,000 after phase two.
Sigdel also said underground work for six floodlight towers is complete, with three towers already in Nepal. A total of 420 floodlight fixtures are being imported from Europe. The stadium’s total projected cost is Rs 6 billion across two phases.
The goal is to host the second edition of the Nepal Premier League (NPL) at the ground once phase one is done. However, the current lease agreement between the Cricket Association of Nepal (CAN) and Tribhuvan University expires in April 2026. Officials have recommended initiating talks to renew the agreement.
The visiting team included MPs, Ministry of Sports officials, and CAN Secretary Paras Khadka. Speaking after the inspection, Chair Gaire said work was progressing despite weather challenges. Khadka reaffirmed CAN’s commitment to finishing the project and expanding similar grounds nationwide.