Kathmandu, Nov 25: The government is preparing to terminate contracts with construction companies falling behind schedule on the Kathmandu-Tarai Madhesh Expressway, a national pride project being built under the management of the Nepal Army.
Infrastructure Development Minister Sunil Lamsal warned contractors last week, during the breakthrough ceremony of the Mahadevtar tunnel, that contracts would be terminated if they failed to meet revised construction schedules. He singled out packages 9A, 9B and 8B for poor performance. National Planning Commission member Arjun Jung Thapa also expressed dissatisfaction with progress on packages 6 and 9.
Lamsal said negligence by some contractors had undermined the entire project despite repeated warnings, site inspections and extensions. The Nepal Army had offered contractors several opportunities and concessions, but progress remained inadequate. He has directed authorities to terminate contracts and invite fresh bids if substantial improvement is not achieved by mid-June.
Thapa has also called for giving underperforming Chinese and Nepali-Chinese joint venture contractors another one to one and a half months to improve before terminating their contracts. The government is considering a reward and penalty system, including waiving penalties for contractors completing work on time while terminating contracts with those failing to deliver.
Of the expressway’s 13 packages, construction contracts have been awarded for 12. Chinese, Indian and Nepali-Chinese joint venture companies are working on these sections.
Jiangxi-Hanuman-Baniya JV is handling package 9A, while XCGC-Hanuman-Baniya JV is responsible for 9B. Both involve Chinese and Nepali contractors. India’s KMC Construction Ltd is working on package 8B, while China First Highway is responsible for package 6.
Chinese companies have been awarded six packages. China State Construction is handling package 1, Poly Changda packages 2 and 4, CAMCE-SDLQ JV package 5, and CREGC-COVEC JV package 10. The main tunnel sections have reported encouraging progress.
Five other packages are being handled by Nepali-Chinese joint ventures: Kumar-Roshan-Sichuan JV on package 3, Xinrung-Ashish-Tundi JV on package 7 and Longjian-Bhimeshwor JV on package 8A, alongside the two joint ventures on packages 9A and 9B.
However, procurement for package 11, covering Khokana, Bungamati and Dukuchhap, has yet to begin, even after a decade. Disputes over land acquisition and compensation, along with concerns about protecting the cultural and archaeological heritage of the local Newar community, have stalled the 6.5-kilometre section. Project chief Brigadier General Bharat Lal Shrestha said efforts were underway to resolve the disputes before starting the tender process.
The 71-kilometre expressway has achieved 51 per cent physical progress. Six of its 14 tunnels have been excavated, including both Mahadevtar tunnels. Contracts have been awarded for bridges at 85 of 89 locations, with foundation work completed at 57 sites and superstructures at 16.
The project’s revised cost estimate stands at Rs 211.93 billion, of which Rs 95.16 billion has been spent. The government has extended the completion deadline for a third time, setting the new target at the end of Chaitra 2086.