Kathmandu, 20 March: The construction of Mainahiya-Sampatiya 132 kV transmission line deemed important for the exchange of electricity between Nepal and India has gained momentum. The double circuit transmission line linking Mainahiya in Rupandehi district of Nepal with Sampatiya (New Nautanahawa) in Uttar Pradesh (UP) State of India has achieved 60 per cent progress in construction, according to the Nepal Electricity Authority (NEA). Target has been set to complete this project within mid-July, 2023.
Foundation has been laid for 44 of 96 towers that will be erected across the 28-km transmission line. Similarly, five towers have already been installed. A team comprising secretary at the Ministry of Energy, Water Resources and Irrigation Devendra Karki, board members of the NEA, executive chairperson among others recently made oversaw the project works and instructed for the timely completion of the project. Stating that the transmission line was an important for exchange of energy between Nepal and India, the team urged the project management to complete the project within the deadline.
People’s News Monitoring Service








Login to add a comment