Second largest Inruwa substation completed 

Kathmandu, 17 October: To strengthen the electricity transmission and distribution system within the country, the construction of 400 KV Inruva Substation has been completed in Bhokraha Narsingh Rural Municipality-4 of Sunsari. Construction of the second-largest 400 KV substation in Nepal, based on a gas-insulated system (GIS), was completed and charged on Monday.

For east-west electricity supply and electricity trade with India, Dalkber is the first automatic substation in the country, and Inruwa is the second largest substation with GIS technology. Another substation of 220/132/33 KV has been commissioned in Inaruwa.

The 400/220 KV Inruwa Substation constructed under the Hetaunda-Dhalkebar-Inruwa 400 KV Substation Expansion Project has three power transformers of 315 MVA capacity. The capacity is 945 MVA. After the construction of the Inruwa-Dhalkebar 400 KV transmission line is completed, around 4000 megawatts of electricity can be exchanged from the Inruwa substation. The wire-pulling work on the Inruwa-Dhalkebar transmission line is going on now.

People’s News Monitoring Service

Conversation

Login to add a comment