Nepal Army says fast track will be completed in extended period

Kathmandu, 11 September: The Nepal Army, which has taken responsibility for the construction of the Kathmandu-Nijgadh Fast Track, said it will complete the construction works by April 2027, a two-year extended period.
Until now, 26.14 percent of the construction works have been completed, said project chief Major General Kamalbikram Shah at a press conference organized on Sunday Afternoon at the Nepal Army headquarters.
He informed that to complete the construction in the added period, the construction project has been divided into 11 clusters and 13 construction packages and works are in progress on No 1 to No 7 packages.
He informed that the construction process has already been started at around 95 percent of the construction packages.
Due to the dispute on the acquisition of land in the Khokana area, works have been kept pending until resolving the problem.
Out of 6415 KM tunnel roads, 2.667 KM tunnel roads have been constructed, he informed.
The total length of the fast track will be 70.977 KM, he informed.
The construction works should have been completed by August 2023, however, due to the Covid-19 pandemic and other obstacles, the construction works were delayed. However, he claimed that the project would be completed within years of the extended period.

People’s News Monitoring Service