MCA Nepal Compact cancels transmission line construction contracts under MCC

Kathmandu, 13 October: All the contracts for the transmission line construction project under the Millennium Challenge Corporation have been cancelled. Millennium Challenge Account (MCA) Nepal issued a notice today informing that all these contracts have been cancelled.

MCA Nepal has informed that the contract has been cancelled as the bidders have offered a very high cost compared to the cost estimate made before bidding for these contracts. Now a new tender for the transmission line contract has to be called.

MCA Nepal proposed to cancel the process after the lowest offer in the tender was 66 percent higher than the estimated cost. MCA Nepal informed that the contract was cancelled after the MCC headquarters approved this proposal.

MCA Nepal had invited bids for the construction of the 315 km long transmission line project divided into three parts. According to the tender that was opened on 8 June, 6 companies submitted proposals to build the transmission line. Out of that, only five companies were technically successful. India’s Kalpataru Power Transmission Limited, Transrail Lighting Limited, Tata Projects Limited, KEC International Limited, Larsen & Turbo Limited were technically successful, and those companies applied for all three packages.

People’s News Monitoring Service