Home / Political News / Current News / Tatopani trading point reconstruction in full swing
Machhapuchre Bank

Tatopani trading point reconstruction in full swing

Kathmandu, 26 May:  The infrastructural development works are taking place in a full swing in Tatopani  as part of the preparation for the resumption of checkpoint which was shut following the Gorkha earthquake-2015.The task of high-tech dry port is almost complete while border bridge construction is also closer to completion.

According to engineer Pradeep Niraula informed that the Chinese government was constructing the road stretching from Baseri of Araniko Highway to Border Bridge while the Road Division Office, Dailekh is building the part from border bridge to Barhabise. The installation of Bailey bridge has been carried out over the Sadhi River in Khursanibri of Barhabise, he shared.

People’s News Monitoring Service

Check Also

Happiness of Nepalis being gauged

Kathmandu, 23 June: The government has decided to survey the happiness of Nepali citizens.In oreder …